> Application forms
 > Conditions &
    Miscellaneous Charges 
    for supply of Electrical
    Energy
 > Frequently asked     questions
 > Revised Tariff    
 > Know your estimated
    Consumption
 > Request for E-Bill
 > Dos & Don'ts
 > The Electricity (Supply)     Act, 1948
 > The Electricity Act, 2003
 > Commercial & General
    Circulars
 > Contact your nearest
    Office
 > Related Links
 > Schedule of Planned     Load Shedding
 > Daily Generation &     Demand
 > T&D Losses

 
 


 
 
Petition
  Petition requesting approval of Fuel & Other Cost Adjustment (FOCA formula and Fuel & Other Cost Adjustment charge for increase in costs during 2000-01

  Section 1. Background
  The tariff for electricity had a component called Fuel Cost Adjustment (FCA). The FCA included expenses on coai, furnace oil and other oils consumed in the power stations together with cost of transportation of fuel and'other incidental charges. It also included cost on staff directly utilised on the coal handling equipment. The FCA was determined on month to month basis on actual expenses upto previous month and projected expenditure thereafter. :

The Government of Maharashtra (GoM) had appointed a Committee under the Chairmanship of Shri V.G.Rajadhyaksha to make recommendations, interalia, to improve the finances of Maharashtra State Electricity Board (MSEB). In its Report, the Committee suggested that the scope of the then existing Fuel Cost Adjustment component should not only cover the incremental fuel and other related costs but also cover other costs which were outside the control of MSEB. The GoM accepted this recommendation of the Committee and it directed MSEB to examine the legal aspects of expanding the scope of the FCA. Subsequently, MSEB took legal opinion, which indicated that in the light of the various courts' judgements d the provisions of the Electricity (Supply) Act, 1948, the Board could impose such a surcharge to recover additional costs so as to maintain the statutory surplus as per provisions of Section 59 of the Electricity (Supply) Act, 1948.

MSEB then submitted a proposal to GoM to expand the scope of the then prevailing FCA to cover non -controllable elements of costs which the Board proposed to call Fuel and 'Other Cost Adjustment (FOCA). The GoM accepted MSEB's proposal and agreed that FOCA should be introduced.

In its Tariff Order dated May 5, 2000, the Maharashtra Electricity Regulatory Commission (MERC) has directed MSEB to provide data related to the FCA every quarter. The MERC has also directed that FCA should not be charged by MSEB ,vithout prior approval of MERC and that the MERC would prescribe the methodology for charging the FCA. Accordingly, MSEB has not charged any FCA in the tariff during 2000-01 so far.

For the quarter ending June, MSEB submitted its calculations for FCA to the Commission in the first week of August 2000. For the quarter ending September 2000, data relating to FCA was again submitted to the Commission in the last week of December along with a proposal to charge FCA on consumption from the month of December onwards up to March 2001. Following a meeting with the Commission, various additional inputs were required from MSEB, vide letter, dated 25/01/2001. Accordingly a revised proposal including a generalised formula was submitted to the Commission on February 12 2001. The revised proposal also included updated calculations of FOCA for period May 2000 to December 2000 in accordance with the proposed formula. The Commission issued a letter dated February 22, 2001 requiring, interalia, a Supplementary Note providing certain details. The Supplementary Note was submitted and discussions for two days were held on March 12 and 13, 2001. During the discussions along with the Commission members, Prayas and Thane Belapur Industries Association also made suggestions on MSEB's proposal.

Accordingly, based on the discussions, this revised petition for approval of FOCA formula, and FOCA calculation for the period May to December is being submitted.
  Section 2. Objective of FOCA:
  MSEB's tariffs for an ensuing year would be determined by MERC based on the estimated costs for the ensuing year. In estimating the costs, a number of asumptions are made. The actual costs incurred by MSEB may be different from the estimated costs based on the assumptions. The Fuel and Other Cost Adjustment (FOCA) formula is being designed to enable adjustments in tariffs to reflect changes in costs that are due to reasons beyond MSEB's control. This is in accordance with the "cost plus" philosophy of tariffs, reficcted in Section 59 of Electricity Supply Act (1948).
   
 

 



 
| ABOUT MSEB | CONSUMER SERVICES | SUPPLIER SERVICES
| FOR INVESTORS |
| CONTACT US | HOME | SITEMAP
| ENGLISH | MARATHI |

Copyright © 1999-2000 MSEB, All Rights Reserved