MAHARASHTRA
STATE ELECTRICITY BOARD
"Prakashgad", 4th Floor, Prof. Anant Kanekar Marg,
Bandra (East), Mumbai - 400 051.
Tel,: (P) 644 37 53 (0) 642 2211
Fax: (022) 645 52 37 Gram :"MUMBAIGRID
|
|
Sub:- FCA rate for December 2000 - March 2001.
Sir,
The
details of estimation of FCA rate for July, 2000 - March,
2001 considering actuals for quarter ending June 2.000, alongwith
a self explanatory note on the proposed methodology was submitted
to the Hon'ble Commission vide letter No-MERC/FCA/32865 dated
14-8-2000 for approval. Approval of MERC on this proposal
is still awaited.
Now,
in continuation thereof and as directed by the Commission
in its order of 5-5-2000, data relating to FCA for the quarter
ending September, 2000 alongwith estimation of FCA rate for
October, 2000 - March, 2001 is submitted herewith. As October
and November is already over, the FCA will be charged for
the consumption in the month of December 2000 and onwards.
FCA
rate for December 2000 to March 2001 has been computed on
the following
basis:
1) The
actual generation and purchase for the period May, 2000 to
September,___ 2000 is deducted from the figures adopted for
May, 2000 March, 2001 based on MERC approval (Statement 1)
to arrive at the generation and purchase for the period October,
2000 - March, 2001.
|