The
First Schedule
Electricity
(Supply)
(c) in the application of clause (a) of paragraph XII, the costs of
production at each of the several controlled stations shall be separately
ascertained, and in the application of clause (c) of the said paragraph
-
(i) the sums ascertained in accordance with clause (a) of
paragraph I of the Eight Schedule in respect of each of
the several controlled stations shall be separately allocated
between fixed costs and running costs, and
(ii) the sum of the several fixed costs and the sum of the
several running costs shall be the fixed costs and the running
costs respectively of the combined station;
(d) in directing the operation of the combined station under
clause (b) of sub-paragraph (1) of paragraph I, the Board
shall have regard to the nature and capacity of the licensee’s
transmission system interconnecting the several controlled
stations and to the requirements of the licensee at each
of those stations.
VIII.In the event of the licensee failing, except where
prevented by causes beyond his control, to perform or continue
to perform any obligation imposed upon him under this Part,
the Board may give notice to him in writing that on the
first day of the licensee’s next succeeding year of account
the generating station will be purchased by the Board, and
on such day the Board shall purchase the station at a price
determined in accordance with the Fourth Schedule, and thereafter
-
(a) all the provisions of this Schedule except paragraph
II and this paragraph shall, in relation to the licensee,
cease to have effect;
(b) the Board shall supply the licensee with the electricity
required by him under paragraph II at such price and on
such conditions as the Board may determine.
PART
II. – Price to be paid for electricity supplied by the Board
under Part I
IX. There shall be agreed between the Board and the
licensee in respect of each month of the licensee’s year
of account -
(a) the maximum capacity of the station, that is to say,
the maximum capacity (expressed in kilowatts available for
supply to feeders) of such plant and works appertaining
to the generation of electricity at the station as were
available for reliable and regular commercial operation
on the first day of the month, including the capacity of
such plant and works as were temporarily out of commission;
(b) the number and size of units of plant and works, forming
part of the aforesaid plant and works, which ought properly
to be deemed to be standby if the station were not a controlled
station;
(c) the standby capacity of the station, that is to say,
the number of kilowatts (expressed in kilowatts available
for supply to feeders) by which the maximum capacity of
the station would be reduced if the standby plant and works
referred to in clause (b) were to be left out of account;
(d) the actual effective capacity of the station, that is
to say, the number of kilowatts by which the maximum capacity
exceeds the standby capacity.
X. (1) The licensee shall be entitled to purchase from the
station in each month at a price determined under paragraph
XIII a number of kilowatts not exceeding the schedule effective
capacity of the station on the first day of that month as
determined in sub-paragraph (2).
(2) The scheduled effective capacity of the station shall
be agreed between the Board and the licensee in respect
of each month of the year
of account, and shall
be computed in the same manner as the actual effective capacity
under paragraph IX, except that there shall be left out
of account such units of plant and works, if any, forming
part of the plant and works referred to in clause (a) of
the said paragraph, as the licensee declares to the surplus