The Ninth Schedule
II.
Of the cost of production of electricity at a generating station
ascertained in accordance with the Eight Schedule, the following
costs, charges and allowances in respect : --
(a) of the costs, charges and allowances set out in clause
(a) of paragraph I of the said Schedule, portions calculated
from the appropriate for mulae set out in paragraph III;
(b) the whole of the costs, charges and allowances set out
in the remaining clauses of paragraph I of the said Schedule.
III.
The portion of the following costs, charges and allowances
to be allocated as fixed costs shall be ascertained from the
formula hereinafter set out against each, namely : --
(a)
cost of fuel 100
100+12.8L
(b) cost of oil, water and stores 100
100+9.66L
(c) salaries and wages 100
100+0.38L
(d) cost of repairs, maintenance and renewals
100
100+0.000INL
Where
–
1[L
= the percentage average load factor of the station;]
N = the number of hours during which the station was in commission
in the year of account.
IV. The amount of the difference
between the costs of production at a generating station ascertained
in accordance with the Eight Schedule and the fixed costs
in respect of the year of account determined in accordance
with this Schedule shall be allocated as ‘running costs;
V. The foregoing provisions
of this Schedule shall not apply in any case where it is agreed
between the Board and the owner of the station that the circumstances
or conditions of operation in the station, whether temporary
or continuing, are such that the said provisions ought not
reasonably to be applied; and in such case the allocation
between fixed costs and running costs shall be made in such
manner as the Board and the said owner may agree.
1 subs. by act 30 of 1966.23,for "L=the average load factor
of the
satation".
|