> Application forms
 > Conditions &
    Miscellaneous Charges 
    for supply of Electrical
    Energy
 > Frequently asked     questions
 > Revised Tariff    
 > Know your estimated
    Consumption
 > Request for E-Bill
 > Dos & Don'ts
 > The Electricity (Supply)     Act, 1948
 > The Electricity Act, 2003
 > Commercial & General
    Circulars
 > Contact your nearest
    Office
 > Related Links
 > Schedule of Planned     Load Shedding
 > Daily Generation &     Demand

 
 


 

Departmental Circular No.326

Statement for Guide-lines 

Following are the guidelines to settle issues relating to arrears and concessions to sick LIS (both HT & LT) with a view to either revive them or close and avoid further losses to the Board. The Guide- lines are based on Board resolution No.1363 of 14-12-1978 and as notified vide Departmental Circular (Com) No.PR-3-LIS/2809 dated 16-1-1979.

1. L.I.S. which want to-revive: 
1) No D.P.C. and no interest on D.P.C. to be levied.

2) Interest at 18% to be levied on the power bill (instead of 24% wherever applied).

3) Actual energy charges to be paid at least 25% in cash before availing the supply and the balance 75% to be paid within the period of two years in suitable monthly/quarterly or half-yearly instalments. These instalments may be granted by Zonal C.Es.

4) No minimum to be recovered for the period of closure i.e. total amount of the bills towards minimum charges, interest, D.P.C., meter rent to be waived for such period. 

5) The period of agreement be extended corresponding to the period of closure. In other words, the consumer would be bound to operate the LIS for a total period of 7 years and accordingly the period of agreement be extended.

6) During the extended period of agreement the 15% of the capital cost, tariff minimum or actual energy charges billed, whichever is higher will apply.

7) In case of default in payment on rescheduled dates (instalments) interest @ 24% (penal rate) should be recovered from the consumer.

8) The above would apply even in case of L.T. scheme which have not availed of supply at all from the beginning. Even such LIS would be treated as sick for the purpose of these guide-lines.

L.I.S . which do not want to revive: 

1) Wherever the distribution fine is not at all used bo revive within a month, and does not agree to the instalments prescribed by the Board for payments of arrears, the line will be dismantled at their risk and cost. If there is no reply, supply to be disconneted and the line to be dismantled and material to be removed for use on other works.

2) The final amount of the outstanding dues to be worked out taking into account the cost of dismantling also.

3) After working the above amount, it should be ascertained whether the LIS has any assets from which cost could be recovered in case the Board seek and obtain a court decree. 

4) In the light of the above data, legal opinion to be obtained as to the cost of court litigation and whether it is worthwhile proceeding against the LIS in the court of law.

5) Where it is considered not worthwhile or desirable to go to court, discussions to be held with LIS to find out to maximum possible recovery of dues. In working out the amount the depreciation and the dismantling cost of the line should at least be recovered.

6) Where even this is not possible, steps to write off the amount of the outstanding be taken, within the delegation of power of the Zonal Chief Engineers themselves. In the remaining cases self contained note be submitted to the C.E (RE & Com) who would take action as per the existing delegation of powers to get the outstanding written off.

III. LIS in State Sector belonging to IDCOM: 

The Board should offer the same package deal of incentives (as in case of I & II above) provided the State Govt. agrees to treat the whole amount of Rs. 148 lakhs given earlier to the Board as a non-refundable grant.

IV. All LIS belonging to Zilla Parishad to be treated as non- IDCOM, except that in the case of closed units, the entire amount is recoverable and the question of negotiating the issue should not arise. 

V. Wherever any LIS requests for reduction in Connected Load /Contract Demand and where it is agreed to by the competent authority, the same should be given effect to, from the date of the application from the concerned LIS.

The modifed guide-lines are communicated vide Circular issued under PR-3/LIS/2809 dt. 16-1-1979. 

The Board further directed that a quarterly report should be submitted by the Zonal Chief Engineers to the Chief Engineer (RE & Com) who would submit consolidated report for all Zones to the Board showing the details of the number of cases decided under their scheme.


Back
Table Of Contents
Next

 
| ABOUT MSEB | CONSUMER SERVICES | SUPPLIER SERVICES
| POWER PROJECTS |
| CONTACT US | HOME | SITEMAP
| ENGLISH | MARATHI |

Copyright © 1999-2000 MSEB, All Rights Reserved