............In
view of the above modifications issued so far the
correct uptodate position in respect of NOC to be
obtained from MPCB and Environment Department in the
case of industries is as follows:
| 1. |
a. |
Medium
and large scale industries which fall under
the 31 industries specified in the said list
(see 4 above) are required to obtain
(NOC/Clearance from MPCB as well as Environment Department
before power supply is released to them.
|
| |
b. |
SSI
industries failling under the 31 industries
specified in the list are required to obtain
clearance/NOC from the MPCB only and clearance
from Environment Department is not necessary.
|
| 2. |
Medium
& large scale industries which do not fall
under any of the 31 industries specified by
the Govt. are required to obtain clearance/NOC
from the MPCB whereas clearance from the Environment
Department is not necessary.
|
| 3. |
All
small scale industries which do not fall under
any of these 31 categories are required to submit
an application in the prescribed format to the
MPCB for getting NOC/ clearance and after confirming
that such an application is submitted, further
action for supply of power to them can be taken.
|
| 4. |
Small
scale chemical industries which are not located
in the coastal area are required to obtain NOC/clearance
from the MPCB before power supply is given.
|
............Member
Secretary, MPCB vide letter No. WP/TB/B/3389 dt. 29-10-88
has further clarified that the electronic units not
carrying out surface treatment like electro-plating
etc. need only apply to MPCB for NOC/clearance and
that the power supply may be given on getting proof
of such application having been made to MPC6 without
waiting for its clearance.
............These
instructions are to be complied with scrupulously
by all the concerned.
............In
view of the above suitable action may be taken in
respect of all applicants for industrial power as
far as NOC/clearance from MPCB and Environment Department
is concerned.
|
Sd/-
|
|
Chief
Engineer (Com)
|
|