Office of the Technical Director
(EHVP - COM)
Maharashtra State
Electricity Board
“Prakashgad”, Bandra (East), Mumbai
-400051.
Tel.:(P) 26472645 (O) 26474211 Fax: (022) 2642366
REF.: PR – 3 / AG
/07717
DATE: 15/03/2003
DEPARTMENTAL CIRCULAR (COMMERCIAL) NO. 672
Subject: Release of power supply on priority
basis to agricultural consumers.
---- “KRISHI – VIKAS 2003
SCHEME”
The
total number of agricultural consumers in the State, though is maximum among
all other State Electricity Boards, the number of prospective agricultural consumers
who have completed all the formalities, including payment & submission of
Test Report, is also considerably large. Any abnormal delay in getting power
supply sometimes results in increase in tendency to obtain the same illegally,
resulting in undesired strain on our Distribution System and also adversely
affects the “Transmission & Distribution Loss” in the system. There is also
consistent demand from the prospective agricultural consumers for expeditious
release of power supply against payment of capital cost, instead of only normative
Service Connection Charges payable as per the prevailing provisions.
In view of the
above and as approved by the Board vide B. R. No. 737 dated 26/02/2003, it has
been decided to introduce a scheme ‘KRISHI – VIKAS 2003 SCHEME”, which will
facilitate the prospective agricultural consumers to get the power supply quickly.
The salient features of the said scheme are as follows:
1.
The
Scheme will be called as “KRISHI – VIKAS 2003 SCHEME” and consumers having connected
load up to & including 5 HP will only be eligible for the said scheme.
2.
The
scheme will be implemented as per the following schedule:
| Sr. No. |
ACTIVITY |
TIME LIMIT |
| 1. |
Acceptance of applications, complete in all respect. |
15/04/2003 |
| 2. |
Survey & issue of firm quotation |
15/05/2003 |
| 3. |
Payment of necessary charges & completion of
other formalities, like submission of Test report, execution of agreement,
etc. |
30/06/2003 |
| 4. |
Release of connection under the Scheme |
30/09/2003 |
3.
The
other details of the Scheme are as follows:
(A)
ZERO POLE CASES:
a)
For those who have applied
& have paid the Charges:
1)
Connections
to be released immediately within three months after payment of normal service
connections charges as per Conditions of Supply,
b)
For those who have applied,
paid the charges and are availing electric supply illegally:
1)
Connections
to be released immediately within three months after payment of normal Service
Connection Charges as per Conditions of Supply, plus
2)
Penalty
amounting to six month’s bill (as per MERC rates), plus
3)
Compounding
fee: (i) up to 3 HP: Rs. 1,000/-
(ii) up to 5 HP:
Rs. 1,500/-
c)
Those who have not applied
for connection, but are availing power supply illegally:
1)
Connection
to be released immediately within three months after payment of normal Service
Connection Charges as per Conditions of Supply, plus
2)
Penalty
amounting to six month’s bill (as per MERC rates), plus
3)
Compounding
fee: (i) up to 3 HP: Rs. 2,000/-
(ii)
up to 5 HP: Rs. 3,000/-
(B)
OTHER THAN ZERO POLE CASES:
(a)
For those who have applied
and paid the charges:
1)
Connections
to be released immediately within three months after payment of Normal Service
Connection Charges as per Conditions of Supply, plus
2)
Payment
of Rs. 6,000 per pole up to 5 poles (up to 300 mtrs).
(b)
For those who have applied
and paid the charges, but are availing power supply illegally:
1)
Connections to be released
immediately within three months after payment of Normal Service Connection Charges
as per Conditions of Supply, plus
2)
Penalty amounting to six months
bill (as per MERC Rate), plus
3)
Compounding Fee:
(i) up to 3 HP: Rs. 1,000/-
(ii) up to 5 HP:
Rs. 1,500/- plus
4)
Payment of Rs. 6,000 per pole
up to 5 poles (300 mtrs).
(c)
For those who have not applied
but are availing electric supply illegally:
1)
Connections
to be released immediately within three months after payment of Normal Service
Connection Charges as per Conditions of Supply, plus
2)
Penalty
amounting to six months bill (as per MERC Rate), plus
3)
Compounding
Fee: (i) up to 3 HP: Rs. 2,000/-
(ii) up to 5 HP:
Rs.3,000/- plus
(4)
Payment
of Rs. 6,000 per pole up to 5 poles (300 mtrs).
In
all the above cases (Zero Pole & other than Zero Pole), the Board has further
directed that the connections will be released only after completion of all
other formalities, like submission of Test Report, Payment of security deposit,
Agreement Fee, Capacitor Testing Fee, Meter Cost, etc. as per the Board’s Conditions
of Supply.
All the Field
Officers are instructed to take due note of the provisions of the “KRISHI VIKAS
– 2003 SCHEME” as above and to initiate all such actions, as may be necessary,
to ensure success of the scheme.
TECHNICAL DIRECTOR (EHVP – COM)
|