Office of the Chief
Engineer (Commercial)
Maharashtra State Electricity Board
"Prakashgad", Bandra(East), Mumbai -
400051.
Tel.:(P)26474753 (O) 26474211 Fax: (022) 26472366 |
REF.: Co.Ord-Cell /Gen Gudl/DGS/ Elect Act 2003/33049
DATE: 15/10/2003
GENERAL CIRCULAR (COMMERCIAL) NO. 380
Sub: GENERAL GUIDELINES IN RESPECT OF STANDBY D.G SET
(Referred with Electricity Act 2003)
Consent / permission Under Section
44 of Electricity (supply) Act 1948 for Standby Diesel generating set for standby
to Board / licensee supply
The New Electricity Act 2003, replacing
the Indian Electricity Act 1910, Electricity (Supply) Act 1948 and Regulatory
Commission Act 1998 has come in force from 10.06.2003.
A condition of “ Consent / permission for installation
and commissioning for Standby Diesel Generating set, Standby to the Board's
supply ” was in existence, as per the provision of section 44 of Electricity
(supply) Act 1948.
Now, as per Section 7 of Electricity Act 2003
any individuals is not required to obtain the consent / permission for the installation
/ operation and maintenance of Generating set. However in-relation with connectivity
of generating set standby to Board's supply, following Guideline may be observed.
1.
No consent
is required for installation / operation and maintenance of generating set as
standby set for self use as per Section 7 of Electricity Act 2003.
2.
As far as connectivity
is concerned with the generating set for self use, as standby to MSEB supply
it should be observed strictly in relation with unit generated through generating
set, unit consumed from MSEB supply and the monthly information should be updated
and maintained at billing unit.
3.
Concern S.E
/ E.E will have to maintain the record for the same and necessary action required
to be effected in proper accounting of consumption of Board's supply
4.
Any further
guidelines from GOM / MERC will be effective as and when available with this
office and will be intimated accordingly.
All the concerned are requested to take note of
the General Guidelines in respect of Standby D.G set for Standby to Board's
supply, for proper implementation, till further guidelines.
T.D (EHVP- COMM, TR)
|