> Application forms
 > Conditions &
    Miscellaneous Charges 
    for supply of Electrical
    Energy
 > Frequently asked     questions
 > Revised Tariff    
 > Know your estimated
    Consumption
 > Request for E-Bill
 > Dos & Don'ts
 > The Electricity (Supply)     Act, 1948
 > The Electricity Act, 2003
 > Commercial & General
    Circulars
 > Contact your nearest
    Office
 > Related Links
 > Schedule of Planned     Load Shedding
 > Daily Generation &     Demand

 
 


 
20. Meters :
a) Correctness of meter
 
i)

Accuracy of the amount of energy supplied to a consumer shall be ascertained by means of a correct meter which may be hired from the Board or purchased by the consumer at the latter's option. In the latter case, the make and type of the meter shall be subject to the approval of the Board. Where the meter is hired from the Board, the Board shall keep the meter correct and in default of its doing so, the consumer shall for so long as the default continues, cease to be liable to pay for the hire of the meter.

ii)

Where the meter is the property of the consumer, he shall keep the meter correct and in default of his doing so the Board may cease to supply energy through the meter after giving him 7 days notice.

iii)

Should the consumer disputes the accuracy of the Board's meter/meters, he may, upon giving notice and paying the prescribed fee, have the same tested by the Board or the Electrical Inspector of Maharashtra State in accordance with section 26 of the Indian Electricity Act 1910. In the event of the meter being tested and found to be incorrect, the cost of testing and all reasonable expenses incidental thereto shall be met by the party to whom the meter belongs and the amount of the bill adjusted in accordance with the result of test taken with respect to the meter readings of the 3 months prior to the month in which the dispute has arisen due regards being paid to the conditions of working accuracy, etc. during the month under dispute, and during the previous 3 months. In the event of the test being undertaken by the Electrical Inspector and the meter being found to be incorrect, the period during which the meter shall be deemed to have been incorrect and the amount of energy supplied to the consumer during the period shall be decided by the Electrical Inspector whose decision shall be final.

iv)

The Board shall at any reasonable time and on informing the consumer of its intention have access to and be at liberty to inspect and test and for that purpose, if it thinks fit, take off and remove any meter to its laboratory.

v)

In case of high tension consurner the Board shall as tar as possible provide the H. Tmetering equipment for registering the demand as well as the energy consumed. The Board may however provide, in the case of smaller loads of less than 500 KW demand supplied at high tension, metering on the low tension side to economise on the cost of H. T. metering equipment or when such H. T. metering set not readily available, in which case H. T. reading for billing purposes will be computed by adding 2% to the L. T. demand reading to determine the KW or KVA billing demand and 5% to the L. T. KWH reading to determine the total energy consumption.

vi)

In case where Power Factor cannot be ascertained from the metering equipment installed for registering the consumption, it shall be determined periodically by the Board under normal operating conditions of the consumer by installing the necessary equipment for this purpose in the consumer's premises and the Power Factor so determined shall be considered as the Power Factor of the consumer's installation for all purposes till such time it is again determined unless it can be established that the operating conditions have materialy altered in which case the Power Factor shall be determined as soon as practicable by the Board.


Back
Table Of Contents
Next

| ABOUT MSEB | CONSUMER SERVICES | SUPPLIER SERVICES
| POWER PROJECTS |
| CONTACT US | HOME | SITEMAP
| ENGLISH | MARATHI |

Copyright © 1999-2000 MSEB, All Rights Reserved