7. Service Line Charges For High Tension/Extra High Tension Supply


**a) For High Tension supply other than agricultural pumping loads :

1. H. T/E.H.T. consumers for new or additional demand of Rs. 15,000/-
    1 st 1000 kVA or part thereof.

2. For each additional KVA demand over 1 OOOKVA. Rs. 10 per KVA

b) For H.T./E.H.T. Agricultural Consumers

For new or additional demand of first 500 KVA or part thereof Rs. 1000/-

For each additional KVA demand over 500 KVA demand. Rs. 100/ 100 KVA or part thereof.

*vi) High Tension consumer/s desirous of or in whose case underground service line in part or full is required to be laid, shall be liable on demand to pay the (non-refundable) amounts as service connection charges to meet the entire actual cost of the work involved plus 15% to cover overhead charges.

*vii) If after commencing the supplythe H.T/E.H.T consumer requires an additional load and if for the supply of additional power, the supply lines etc. are required to be strengthened/amended, the entire cost of such strengthening/amending or providing of additional lines, equipments shall be paid by the H.T/E.H.T consumer, subject to same conditions as detailed in 7(i) and 7(v). However, in case of underground service such cost shall be paid by the consumer subject to conditions as detailed in 7(v) and 7(vi).


* Modified Vide B. R. No. 1705 Dt. 16-10-1985
**ModifiedVide B.R.No.514Dt.28-5-1990

Back
Table Of Contents
Next

| ABOUT MSEB | CONSUMER SERVICES | SUPPLIER SERVICES
| POWER PROJECTS |
| CONTACT US | HOME | SITEMAP
| ENGLISH | MARATHI |

Copyright © 1999-2000 MSEB, All Rights Reserved