1. Service connection for low tension supply : 
        
      The Board provides overhead service line free of cost upto 30 metres of service line from its nearest distributing main for purpose other than agricultural pumping. For agricultural pumping purposes the Board provides overhead service line free of cost upto 300 metres. The details of the charges payable by consumers requiring permanent supply have been described in conditions 4 to 7 of the Conditions of supply of the Board.

      Extension or additions if any to meet increased demands will be
charged at the actual cost of materials and labour plus 15% to cover overhead charges. The service connection charges are payable in advance before this work is carried out.
*2. Temporary Service Connection :

Temporary service connecion at L. T. will be given subject to the following conditions.

A) Single phase supply upto 5 KW 
 i)

Period of supply : 

Supply will be giyen for a period not exceeding one month but the supply can be extended for further periods not exceeding one month on each occasion provided surplus power is available.

The definition of month shall be as under "Month means the calender month when the period 
commences from the begining of a calencler month otherwise a period of 30 days".

ii) Service connection charges : 
1 . Fixed service connection charge Rs. 50/ 
2. Rental charge of Rs. 4/- per meter of the line upto the metering point for the first month or part thereof and Rs. 1/- per meter for each subsequent month or part  thereof.

*** iii) Minimum charges    :

Rs. 180/- for a period upto 3days
Rs. 45/- per day thereafter.

**          a)
Energy Charges       : 
200 paise Per Unit.

iv)
Security deposit       : 
Rs. 30/- per 0.5 KW of connected load subject to minimum of Rs. 50/-

B) Three phase supply for connected load more than 5 KW and Cinemas.
i) Period of supply : 

Supply will be given for a period not exceeding one month but the supply can be extended for further periods not exceeding one month on each occasion provided surplus power is available.

The definition of month shall be as under "Month means the calencler month when the period commences from the beginning of a calender month otherwise a period of 30 days".

ii) Service connection charges : 
1 . Fixed service connection charges same as in general condition 5 (a).
2.

In addition, the actual total cost involved for giving connection (Labour & Materials plus 15 per-cent overhead charges) shall be recovered from the consumer. When the service is removed the labour cost for dismantling shall be charged to the consumer who will be allowed a credit for all the materials returned in servicebale condition at the actual cost less 25 percent depreciation for the first month or part thereof and 6.25 percent for each subsequent month/limited to total 100% depreciation. A deposit will be taken prior to the commencement of supply to cover the above charges and adjustments, if any, effected after the service has been removed.

iii) Minimum charges  :  Rs. 600/- for a period upto 3 days.
Rs.180/- per day thereafter.

a) Energy charges : 200 Paise. Per Unit.

iv) Security deposit : Rs. 100/- KW CL or part thereof subject to
minimum of Rs. 200/-
Note : for (2) (A) and (2) (B) - No interest will be payable on such deposit. 

*Modified Vide B.R. No. 1705 Dt. 16-10-85
**Modified Vide B.R. No. 539 Dt. 31-8-96


Back
Table Of Contents
Next

| ABOUT MSEB | CONSUMER SERVICES | SUPPLIER SERVICES
| POWER PROJECTS |
| CONTACT US | HOME | SITEMAP
| ENGLISH | MARATHI |

Copyright © 1999-2000 MSEB, All Rights Reserved