CONDITIONS OF TENDER AND
SUPPLY
1) EFFECT OF CONTRACT :
The contract shall be considered as having come in to
force from the date of Notification of Award. The tenderer whose offer is accepted
is hereinafter called “the supplier”.
2) SECURITY DEPOSIT :
The supplier shall pay within 15 days, security deposit
@ 10% of the value of the order, unless having valid permanent bank guarantee
of Rs. 5(five) lakhs with the Board. The maximum security deposit payable against
the contract shall be limited to Rs. Five Lakhs.
Security deposit applicable to SSI unit in Maharashtra
will be 3% (Three percent) of the order value subject to a maximum of
Rs. 50,000/- (fifty thousand). However, in respect of the following categories
of suppliers, the security deposit applicable shall be as under :
a) For the order value upto Rs. 25,000/-, no security
deposit shall be payable by the registered suppliers on the list of Development
Commissioner (Industries) and Stores Purchase Officer.
b) Small Scale Industries registered with the Directorate
of Industries and Maharashtra Khadi & Gramodyog Mandal shall be exempted
from payment of security deposit for value of order upto Rs. 50,000/-.
The SSI units having industries outside Maharashtra
State will not be eligible for exemption or concession in the security deposit.
They will have to pay full security deposit at 10% of the value of order
limited to Rs. Five lakhs unless having deposited permanent bank guarantee of
Rs. Five lakhs with the Board.
The failure to make payment of security deposit within
15 days as above will be viewed seriously and the contract awarded shall be
liable to be terminated-.
The security deposit shall
be paid in favour of Maharashtra State Electricity Board by way of:
(i) Cash or
(ii) Cheque or demand draft on any scheduled bank in Mumbai or
(iii) When the amount exceeds Rs. 5,000/-, bank guarantee
from a scheduled bank valid for the guarantee period of last consignment of
materials as given in clause no.26 of conditions of Tender and supply in the
standard form of the Board or
(iv) Pledging any of the certificates i.e. National
Plan certificates. National Defense certificates. National Plan savings certificates.
National Savings Certificates and National Defense Deposit certificates or
(v) Fixed deposit receipts of any scheduled bank in
favour of the Maharashtra State Electricity Board or,
(vi) Maharashtra State Electricity Board debentures,
or
(vii) Government securities endorsed to the Maharashtra
State Electricity Board as detailed below:
(a) All the endorsement on G.P. Notes
including the last in favour of ‘Maharashtra State Electricity Board’ should
be certified by the Public Debt Office. Reserve Bank of India or alternatively
a fresh Note from Public Debt Office, Reserve Bank of India should be tendered.
(b) All the interest accrued on the
G.P. Notes till date of transfer should be collected before submission and interest
accruing subsequently will be collected by the Board periodically and credited
to the depositor’s account less 2% subject to the minimum of Rs. 2/-
which will be retained by the Board to cover the cost of collection etc:
This security deposit in cash or in the form of bank
guarantee or otherwise is for the due performance of the material/contract and
the same shall be liable to apportion towards amount due or becoming due by
the supplier on his failure to execute this order or any other contract and
in the event of non fulfillment of the terms and conditions of the contract.
The security deposit shall be refunded
on the expiry of the guarantee period specified in condition No.26 stated herein
below. In case of G.P. Notes the amount of security deposit payable should be
on the basis of market value of the G.P. notes at the time of presentation of
the G.P. Notes.
3) QUALITY OF SUPPLIES :
All materials supplied shall be strictly as per specification
laid down and in accordance with the approved standard samples. In case of any
materials for which there are no standard/ approved samples, the supplies shall
be of the best workmanship and good quality and this office shall be informed
of the progress of manufacture of the material.
4) MATERIAL AND COMPONENTS :
The material and components not specifically stated
in this specification but which are necessary for satisfactory operation of
the equipment/items specified, shall be deemed to be included unless specifically
excluded and shall be supplied without any extra cost.
5) SAMPLE BEFORE COMMENCING BULK SUPPLIES (Wherever
necessary)
(A)
Before taking up the manufacture
of the bulk supply, the supplier shall get one number sample of each item approved
and sealed from the Board’s Executive Engineer (IW) or its authorized representative,
within 15 days from the receipt of the order. No bulk supply should be made
unless the sample is approved by the inspecting officer.
The supplier shall give advance intimation of 15 days from the date of
receipt of order, to the Executive Engineer (Inspection Wing), Maharashtra
State Electricity Board, Central Purchase Agency, 1st Floor, ‘Prakashgad’. Station
Road, Bandra (EAST), Mumbai -400 051,for sample approval. The sample
so approved, shall be a master sample retained for reference purposes, at supplier’s
works till the last consignment is despatched.
The time allowed for, commencing delivery includes the time required
for getting the sample approved as above. If, however, 15 days from date of
receipt of the intimation for sample approval, the period for commencing/completing
the supplies, will be considered to have been extended by the excess time taken
for intimating the approval. If the approval of the sample is not received from
the inspecting officer within 15 days, the supplier shall remind this office
for the same in writing.
(B)
Consignee’s Sample : At the time of inspection, the supplier shall get
approved and sealed by the Board’s inspecting officer, as many samples as the
number of consignees as stated above and each of the approved sample must be
forwarded with the first lot being despatched to the respective consignee together
with the copy of the relevant inspection report and the related test certificates.
6) ACCEPTANCE OF SUPPLIES/INSPECTION :
(a) The supplier shall
normally offer at a time the entire quantity required to be delivered every
month as per the delivery schedule indicated at Sr. No. IV of Annexure ‘B’ for
the purpose of inspection by the Board. However, in exceptional circumstances,
the supplier may be allowed to offer quantity at a time not less than 50%
of the quantity required to be delivered every month.
(b) Materials
shall be inspected by the Board’s Executive Engineer/or the representative authorized
by the Board before despatch. An intimation in the prescribed proforma about
the date on which materials shall be ready for inspection, indicating approximate
quantity, shall have to be given to the Executive Engineer (Inspection Wing),
Maharashtra State Electricity Board, ‘Prakashgad’. 1st floor, Station Road,
Bandra (East), Mumbai - 4.00 051, so as to reach him sufficiently
in advance, failing which, the supplier shall be responsible for delay in delivery
on account of inspection. On receipt of such intimation, the materials shall
be inspected within 30 days. The materials shall be despatched only after inspection
and approval of same by the Inspector. The inspection approval letter shall
be valid for a period of 21 days from the date of issue of letter to enable
the supplier pack the material and arrange transportation thereof within the
said period. After this period of 21 days, the validity of this inspection approval
letter will lapse. Thereafter, the material will have to be offered for re-inspection
at the cost and risk of the supplier. Further the price variation shall be payable
limited to the period of original call letter or the actual date of despatch
whichever is lower and the liquidated damages for late delivery shall be levied
on such delays.
(c) The supplier
shall notify the names of the consignees to whom the inspected lot would be
despatched. The Inspector shall intimate change in destination, if any, at the
time of inspection approval and accordingly the material shall be despatched.
The supplier shall get the copies of inspection approval letter together with
witness certificate duly signed by the concerned Inspecting Officer IN BLUE
INK only and also mention reference or inspection approval letter on the challan/invoice,
failing which any delay occurred in getting the S.R. Notes from the consignees
would be solely to supplier’s account.
(d) In the event,
during the inspection by the Board’s Inspecting Officer, if it is observed that
the quantity actually offered for inspection is less than the quantity indicated
for inspection in the inspection call, the Board shall be entitled to recover
from the supplier, the actual expenses incurred for arranging the inspection,
and the supplier shall not dispute the amount to be recovered.
(e) The supplier
shall submit the test certificates/reports from any approved laboratory or the
laboratory of his own. for the respective quantity of material, before despatch.
The material shall not be despatched unless and until the test certificates
are approved by the Board.
(f) All the necessary
help shall be extended by the supplier to the authorized representative of the
Board to carry out testing of equipment/materials.
7) RIGHT TO CARRY OUT INSPECTION DURING MANUFACTURING:
The Board at its option, will inspect the material ordered
during its process of manufacturing including the inspection of raw materials
and will request the supplier to carry out such tests as may be necessary to
ensure proper quality of the material. The samples of components of the material
shall be subject to quality check by the inspecting officer during manufacturing.
8) RIGHT TO REVISE DESPATCH INSTRUCTIONS, DELIVERY
SCHEDULE AND TO DEFER SUPPLIES:
i)
The Board reserves its right
to revise the despatch instructions issued alongwith the order, at the time
of giving final clearance for despatch after inspection of the material. If
such change in destination is not intimated at the time of inspection approval
or waival of inspection, the supplier shall despatch the material as per the
despatch instruction in accordance with A/T indicated by his in the inspection
call letter.
ii) The Board reserves its right to change the
delivery schedule of the contract either by reducing the monthly lot upto 60%
of the agreed lot or by increasing the same upto 120% of the agreed lot
with prior two months notice and the Board shall not be liable to pay any compensation/damages
on account of such change in delivery schedule.
iii) The Board reserves its right to defer the
balance supply to be received against the order by giving two months notice
for a maximum period of 6 months. In such an event, the delivery period for
the deferred material shall be deemed to be extended proportionate to the period
of deferment and the Board shall not be liable to pay any compensation/ damages
on account of such deferment of deliveries.
9) WAGON
LOADS/TRUCK LOADS :
Quantity to be despatched to consignee may not necessarily
be in full wagon load/truck load and may be part load as per the Board’s requirements.
10) ROAD
TRANSPORT:
In case the supplier prefers to despatch the materials
by road transport at his risk and cost and without any extra cost to the Board,
the materials shall be accepted only during office hours on working days. The
supplier should ensure that the goods reach the stores sufficiently in advance
so as to arrange their unloading during office hours, failing which, the Board
shall not be liable for unloading and for inconvenience caused to the transport
contractor in the form of detention etc. Unloading at stores shall be arranged
by the consignee.
11)
PAYMENT OF FREIGHT CHARGES :
Railway Receipt should be prepaid. In case the freight
is not prepaid, the freight charges paid shall be recovered from the supplier
with additional ‘TWENTY PERCENT’ amount of freight.
12)
CLEAR RAILWAY RECEIPT:
Packing used shall be conforming to specifications/conditions
laid down by the railways and clear railway receipt shall be obtained by the
supplier without any ambiguity, so as to facilitate proper clearance of goods
at destination.
13)
DESPATCH INTIMATION:
The supplier shall inform telegraphically to the consignee
details of despatch giving RR/ LR No., Wagon/Truck No., Type of wagon, craneable
consignment or otherwise, total value of consignment, etc. to facilitate the
consignee to arrange for clearance of goods.
14)
BILL OF MATERIALS:
The supplier shall furnish bill of materials for each
type of equipment/material offered which should be consistent with the drawing,
sample, specification and guaranteed technical particulars. The copies of the
bill of materials should always be enclosed alongwith the bill submitted by
the supplier for payment wherein he should specifically mention the materials/
components despatched out of the bill of materials, if the equipment is not
sent in totality. Where the equipment/material to be supplied consist of more
than one component, the supplier claiming payment for equipment/materials shall
certify that all components of the equipment/ material have been supplied in
full for the quantity indicated in the invoice. Part payment shall not be allowed.
15)
PACKING LIST:
Each package shall contain, in waterproof cover, the
detailed list indicating the order reference, date, list of content and reference
to the approved bill of materials. Each item contained in the package shall
be described sufficiently to enable identification of the quality, weight etc.
There should not be any alteration in the packing list incorporated in the order,
copy of the packing list should be sent to all the consignees, Technical
Director (Stores) as well as Chief Accounts Officer (SB) and should be enclosed
with the bills along with other documents.
16)
VERIFICATION OF MATERIAL SUPPLIED:
The Board shall have the option to carryout various
tests including type tests as per specification on the samples selected at random
from the supplies effected, to ensure that the supplies conform in quality and
workmanship to the relevant specification. The testing shall be done at independent
laboratory at Board’s cost. Due notice shall be given to supplier for such sample
selection and such testing thereof to enable him to be present for the same
if so desired by him. If the supplier or his authorized representative fails
to attend the sample selection and testing, the same shall be carried out unilaterally
by the Board and the result thereof shall be binding upon the supplier. In case
the sample selected from the supplies fails to withstand the required tests,
then
I.
for the first time failure of
sample,
(a)
supplier shall have to replace
the full quantity of the respective inspected lot supplied to various Stores
and lying unused at Stores.
(b)
for the quantity already accepted
against the order and used, deduction in price of 10% of the value of material
supplied shall be made
AND
II.
in respect of further supplies
made against the order, if failure of sample is noticed (i.e. second time failure
against the order)
(a)
the quantity lying unused at
various Stores shall be rejected.
(b)
for the quantity already accepted
against the order and used, deduction in price of 10% of the value of material
supplied shall be made,
(c)
balance quantity against the
order including the rejected quantity shall be cancelled without any liability
on either side,
(d)
the firm will be debarred from
dealing with the Board upto a period of three years from the date of rejection.
17.
REPLACEMENT OF GOODS LOST, BROKEN OR DAMAGED:
Not withstanding anything herein contained, the supplier
undertakes to be responsible for the safe arrival of the materials in good condition
and without any loss or damage at the final destination and until the same be
actually delivered to and received by the Board at its stores or other place
of final destination and for this purpose, materials carried by railways or
other carrier shall be deemed to be so carried at the risk of the supplier.
In case of transit damage/shortages, the payment shall be made only for the
quantity received in good and working condition and the consignee shall lodge
claims with carriers and transfer the same to the supplier with all necessary
documents for settlement of the same with carriers at the supplier’s end. The
transit damages/shortages/losses reported by the consignee shall be repaired/replaced
by the supplier duly inspected, free of cost, within one month from the date
of such intimation of breakages/shortages/losses without waiting for settlement
of the claims from carrier or insurance co. etc.
18)
REPLACEMENT OF REJECTED MATERIALS:
If, on inspection at the final destination, the Board
discovers any loss in the materials supplied or that they are received in damaged
condition or that in the opinion of the Board, they are not of the contracted
quality or specification, the Board shall be entitled (notwithstanding that
the property in the materials shall have passed on to the Board) to refuse to
accept or reject the materials altogether and claim damages or cancel the contract
and buy its requirements from any of its suppliers, stipulating earliest possible
delivery and in accordance with its tender system against the supplier and recover
the damages if any, from the supplier from any outstanding, sums that may be
due to the supplier from the Board against this contract or against any of the
contract entered into with the supplier, without prejudice to other rights and
remedies available to it in law and reserving always to itself the right to
forfeit the security deposit placed by the supplier for the due fulfillment
of the contract.
In case the stores/materials are found not in accordance
with the prescribed specifications and/or the approved sample, the same will
be rejected and the supplier shall replace the rejected stores/materials free
of cost within one month from the date of intimation. The replacement of
goods shall also have to be got inspected as per inspection clause. Further
if the stores/ equipment supplied becomes incomplete on account of either rejection
or short supply of its components, the complete cost of the stores/equipment
shall be recovered from supplier’s bills without notice. .
19)
TOLERANCE IN QUANTITY TO BE SUPPLIED:
Variation in quantity to be supplied against confirmed
order shall be permissible upto FIVE PERCENT PER ITEM PER CONSIGNEE.
20)
OCTROI AT DESTINATION :
Octroi charges, if applicable, at destination shall
be borne by the Board.
21)
MATERIAL DESPATCHED AND PROGRAMME :
A statement as under indicating despatches effected
during every month shall be furnished to this office along with the programme
of manufacturing/despatches during the following two months. In the event of
no despatch, the statement shall contain nil information. This statement should
reach this office on or before 7th or succeeding month addressed to Technical
Director (Stores), Maharashtra State Electricity Board, Mumbai
- 400 051, (Attention : Supdt. Engineer (Stores).
MONTHLY STATEMENT: I.
Name of Supplier:
II.
Reporting Month :
| Sr No. |
A/T No. |
Material |
Item No. as Per A/T |
Consignee |
RR/LR Delivery Challan No. With Date |
Date of Actual Receipt of Material |
Qty. Despatched Between 26th of Preceding month and 25th
of the Reporting month |
Programme of supply during the next
2 months |
| 1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
A consolidated details of the above information shall
be furnished to office of the Technical Director (Stores) after completing
the suppliers of a particular order. The copy of this consolidated .information
shall invariably be forwarded to the respective consignees, failing which,
security deposit paid against the contract shall not be released.
22) SUBMISSION OF BILLS :
No payment shall be made for the supply of equipment/item
in part components.
23) PAYMENT OF BILLS :
100%
payment of the Contract price will be paid by A/c payee cheques within 60 days
from the date of receipt of entire lot as scheduled in commencement period or
in monthly delivery schedule of material at the stores in good condition. The
material is to be tested/ measured by the field Officers/Consignees wherever
provided for Date of issue of cheques shall be the date of payment. Following
documents will have to be forwarded to the Chief Accounts Officer (SB), MSEB,
Prakashgad, Station Road, Bandra(East), Mumbai - 400 051 along with bills in
triplicate with copy to the consignees, to facilitate payment.
(i) Bill/Invoice.
(ii) Certificate of proper despatch
(iii) Zerox copy of despatch document (i.e. RR/LR).
(iv) Inspection/TC Approval.
(v) Other documents like proof of having paid the excise
duty as required under the prevailing rules (In case the supplier is a trader,
these documents from the original manufacturer of the product shall be produced.)
copy of acceptance letter of bank guarantee for security deposit, authority
of exemption thereof.
(vi) Detailed packing list.
(vii) Bill of materials.
(viii)The relevant document in support of price variation
claim.
(ix) Zerox copy of monthly despatch statement required
as per clause 21 above.
(x)
Chartered Accountant’s certificate for having
passed entire MOD VAT benefit to purchaser.
Where required by the Board, the successful tenderer
must send the operation and maintenance manuals, test certificates, drawings
etc. for the material ordered. These should be sent immediately after despatch
of material and a statement to that effect should be made in the invoice. Failure
to comply with this provision will result in delay in payment of the bill.
The supplier shall forward the original R.R./L.R. direct
to the consignee along with various documents as stated below in this clause.
The original bill shall be forwarded to the Chief Accounts Officer (SB), MSEB,
Prakashgad, Bandra(E) and marked ORIGINAL, the bill should indicate the sales
tax registration certificate no. and date held by him under the Sales Tax Act.
The Board shall not be responsible for delay in payment of bills if the supplier
fails to comply with any of the above requirements.
Supplier’s copy of S.R. Note will be forwarded by the
consignees through their respective Major Stores for supplier’s record towards
acknowledgement of receipt of material. Accounts copy of S.R. Note will be forwarded
by the respective Major Stores to C.A.O. (SB) for payment.
In case the supplier is a trader, it shall be imperative
for him to furnish documentary evidence of having paid excise duty by the manufacturer
whose product has been offered.
Wherever the payment is to be effected against Material
Receipt Intimation (MRI) and if the supplier fails to forward the documents
such as inspection report, bill of materials, approved drawings, etc. alongwith
the invoice to the respective consignees, the MRI issued will be a qualified
one and no payment shall be made against the said MRI.
The whole of the first lot as well as monthly lot when
delivered in installments, the date of delivery and due date of payment will
be counted after the receipt of the entire lot along with following documents
complete in all respect by the consignee :
i) Copy of invoice/challan
ii) Packing list
iii) Approved sample (if applicable)
iv) Original copy of RR/LR
v) Inspection approval letter signed by the Inspecting
Officer in Blue ink along with copies of routine/acceptance test certificate
or copy of letter of waival of inspection as the case may be.
The Board at it’s discretion, shall arrange for payments
as above from its own sources or alternatively under ICICI line of credit/IDBI
rediscounting scheme, as per terms of ICICI /IDBI as may be applicable, in which
case, co-acceptance charges/stamp duty shall be to Board’s account.
24) TAXES AND DUTIES :
(A) Notwithstanding the fact that contract price is
inclusive of excise duty and sales tax :
(i) Excise duty shall be only on Ex-works price and
shall be paid/reimbursed at actuals on the basis of due date of delivery, against
documentary evidence.
(ii) Sales tax shall be paid at actuals on the basis
of due date of delivery.
(iii) Variation in excise duty and sales tax on bought
out items shall not be entertained.
(B) Structural changes in and due to ‘MODVAT’
Scheme : -
(i) In the event of any structural change occurred
in the MODVAT Scheme after the date of submission of the tender till the currency
of the contract, the benefit out of such change shall be passed on to either
of the parties.
(ii) In the event of ‘MODVAT’ credit being extended
by the Government of India to more items than those already covered, the firm
should advise the purchaser about the additional benefits accrued or any variation
thereof, through a letter containing the following certificate, as may be considered
necessary by the purchaser.
“We hereby declare that we can avail additional duty set-offs as per
latest MODVAT Scheme in force now and we hereby give a reduction of ....
per unit and agree to revise the prices indicated in the order. The current
excise duty of ...........% is payable on this reduced price. Therefore,
we request you to amend the order accordingly.”
25) DEDUCTION :
Any amount or amounts which become payable by the supplier
to the purchaser under a particular contract, shall be deducted by the purchaser
from any amount/amounts due or becoming due to the supplier under the same or
any other contract and shall be adjusted against dues to the Board.
26)
GUARANTEE:
Goods
offered shall be guaranteed for a period of 12 months from the date of commissioning
or 18 months from the date of despatch whichever is earlier. The stores/
materials found defective within the above guarantee period shall be replaced/repaired
by the supplier free of cost, within one month of receipt of intimation. If
the defective store/materials are not replaced/repaired within the specified
period as above, the Board shall recover an equivalent amount plus 15 % supervision
charges from any of the bills of the supplier.
27)
LIFTING OF REJECTED/DAMAGED MATERIALS :
a) On failure to replace or repair the transit damaged
or rejected material within one month from the date of intimation as required
under tender, it shall be deemed to have concluded that such material is finally
rejected. The damaged/rejected material shall be lifted by the supplier within
30 days from the date of receipt of notice to that effect from the concerned
consignee on reimbursement to the Board of the cost of the material / equipment,
if any, already paid in terms of payment clause in the contract and actual expenses
incurred by the consignee towards octroi, handling, demurrage/wharfage/under
charges freight, insurance premium etc. The board shall not be responsible in
any case for the loss, destruction, damage, deterioration of the material after
expiry of the said 30 days period.
b) If the supplier fails to lift the material within
this period, the material will remain with the Board at the cost and risk of
the supplier. Supplier shall, therefore, be liable to pay ground rent @ 0.1%
per day of purchase cost of the material to be lifted from the date of intimation
of rejection till the actual date of lifting.
c) The Board will be also free to dispose of such
material, after the period of said 30 days by Public auction/Tender notice/Destruction
as may be deemed fit and storage charges @ 0.1 % per day of purchase
cost will be recovered from the date of intimation of rejection of materials
till the date of realization of the sale amount/physical removal of the material
besides the actual expenses incurred as referred to at (a) above.
d) Not withstanding what is contended in the foregoing
clauses, the supplier shall be liable to pay the Board the cost and expenses
incurred by the Board, if any, including ground rent and the same shall be appropriated
and recovered from the sale proceeds.
28)
LIQUIDATED DAMAGES FOR LATE DELIVERY :
In case the materials are not delivered within the period
stipulated in the order, the supplier shall be liable to pay at the discretion
of the competent authority of the Board, the liquidated damages to the Board
upto half percent per week or part of week on the price subject to a maximum
of cumulative ceiling of 10% reckoned on the contract value of such complete
portion or section of the plant, equipment or material, delayed and also the
portion supplied which could not be brought into commission due to any part
thereof not having been delivered in time. Due consideration may be given in
the levy of liquidated damages for reasons absolutely beyond the control of
the supplier, for which documentary evidence shall be produced to the satisfaction
of the competent authority of the Board.
The Board shall be entitled to deduct/recover the amount
of liquidated damages from the current bill payable to the supplier or any other
amount due or payable to him against this or any other contract.
For computing the liquidated damages for delayed supplies,
the date of railway receipt or the date or receipt of materials at stores in
case of road transport, shall be the date of delivery.
In case
the Board does not arrange for inspection of material within 30 days from the
date of receipt of inspection call in its office, the period of more than 30
days will not be considered for levy of liquidated damages. For computing the
period taken for inspection in such cases, the relevant date mentioned in the
inspection certificate issued by the inspecting officer would be considered.
29)
PERFORMANCE OF CONTRACT :
The Board will not be in any way liable for non-performance
either in whole or in part of any contract or for any delay in performance thereof
in consequence of strikes, shortage, non-availability of raw materials, combination
of labour or workmen or lockout, breakdown or accident to machinery or accidents
of whatever nature, failure on the part of the railways to supply sufficient
wagons to carry essential raw materials etc. and finished products from the
stores,
subject to the provision and stipulation made in condition No. 28 as stated
above i.e. Liquidated damages for late delivery.
30)
POWER OF ATTORNEY :
It will be obligatory on the supplier to communicate
the revocation of Power of Attorney, if any after submission of offer till the
execution of contract failing which the act/s & action done by the agent/representative
shall be deemed to be the valid act/s & action of the tenderer/ supplier.
31)
JURISDICTION :
Any disputes or difference arising under, out of or
in connection with this tender or contract if concluded, shall be subject to
the exclusive jurisdiction of the “Courts” in Mumbai.
32)
TERMINATION OF CONTRACT :
In case the contractor/supplier fails to deliver the
stores/material or any consignment thereof within the contracted period of delivery
or in case the stores/materials are found not in accordance with the prescribed
specification and the approved samples, the Board shall exercise in discretionary
power either,
(a) to purchase from elsewhere, after giving due notice
to the contractor, at the risk of contractor, such stores/material not so delivered
or other of similar description, without canceling the contract in respect of
consignment not yet due for delivery,
OR
(b) to cancel the contract reserving Board’s right
to recover damages, notwithstanding that the powers under (a) and (b) referred
above are in addition to the rights and remedy available to the Board under
the General Law of India relating to contract.
NOTES:
(i) In the event of risk purchase of stores of similar
description, the option of the Board shall be final. In the event of action
taken under (a) or (b) above, the supplier shall be liable for any loss which
the Board may sustain on that account but the supplier shall not be entitled
to any saving on such purchases made against default.
(ii)
The decision of the board shall
be final as regards the acceptability of the stores supplied by the supplier
and the Board shall not be required to give any reason in writing or otherwise